2018

Project Started

Feb, 2018(3%)
  •  Mobilization 100%
  •  Site clearing 100%
  •  Piling 40%
  •  Overall progress 3%
Mar, 2018(8%)
  • Mobilization  100%
  • Site hoarding 100%
  • Site fencing  100%
  • Site office  100%
  • Piling  85%
  • Overall progress  8%
Apr, 2018 (12%)
Mobilization 100%
Site hoarding 100%
Site fencing 100%
Site office 100%
Piling 100%
Sheet pile 100%
Overall progress 12% 
May, 2018 (16%)
  • Mobilization 100%
  • Site preparation 100%
  • Piling & Sheet pile 100%
  • Soil protection 50%
  • Overall progress 16%
Jun, 2018 (18%)
  • Soil protection 80%
  • Overall progress 18%
Jul, 2018 (21%)
• Soil Protection 95%
• Foundation 80%
• Overall Progress 21%
Aug, 2018 (26%)
• Soil Protection 95%
• Foundation  90%
• ฺBasement    31%
• Overall Progress 26%
Sep, 2018 (30%)
• Soil Protection 95%
• Foundation  100%
• ฺBasement    52%
• Overall Progress 30%
Oct, 2018 (33%)
• Soil Protection 95%
• Foundation  100%
• Basement    60%
• Overall Progress 33%
Nov, 2018 (36%)
• Soil Protection 95%
• Foundation  100%
• ฺBasement    90%
• Overall Progress 36%
Dec, 2018 (39%)
• Soil Protection 100%
• Foundation  100%
• ฺBasement    100%
• ฺ1st Floor      100%
• Overall Progress 39%
Jan, 2019 (44%)
• Foundation                    100%
• 1st-5th Floor (structure) 100%
• 6th Floor (structure)         60%
• Overall Progress              44%
 
Feb, 2019(50%)
  •  Foundation                       100%
  •  1st-7th Floor (structure)    100% 
  •  8th Floor       (structure)      20%
  •  1st-4th Floor (Architecture) 30%
  •  Overall Progress                 50%
Mar, 2019(56%)
• Foundation                         100%
• 8th Floor(structure)              50%
• 1st-4th Floor (Architecture)  40%
• 5th-6th Floor (Architecture)  20%
• Overall Progress                  56%
Apr, 2019(62%)
• Foundation                             100%
• 8th Floor(structure)                100%
• 1st-4th Floor (Architecture)      70%
• 5th-6th Floor (Architecture)      35%
• Overall Progress                      62%
May, 2019(66%)
- Structure              90%
- Architecture         50%
- Interior                 10%
- Overall Progress  66%
๋June ,2019 (73%)
- Structure              98%
- Architecture         60%
- Interior                 15%
- Overall Progress  73%
๋Jul, 2019 (73%)
- Structure              98%
- Architecture         60%
- Interior                 20%
- Overall Progress  76%
Aug, 2019 (80%)
- Structure              99%
- Architecture         64%
- Interior                 25%
- Overall Progress  80%
Feb, 2020 (100%)
- Structure                100%
- Architecture           100%
- Interior                   100%
- Overall Progress   100%
 
100%

OF OVERALL PROGRESS

As of Feb, 2020