2020

Project Started

30 Nov 2020


Construction progress is 22.8% as of 30th November 2020

- Cap Beam Work: 100%
- Soil Protection: 71%
- Excavation Layer B3: 17%

31 Oct 2020

- Pile wall: 100%
- Cap Beam Work: 98%
- Soil Protection: 23%

Overall progress: 18%

30 Sep 2020
- Piling  100 %
- Cap Beam Work 60%
- Overall progress  12 %
31 Aug 2020
- Mobilization  100%
- Site clearing   100%
- Piling  100 %
-Overall progress  8 %
31 May 2020(1.3%)

FYNN Asoke - Construction progress as of 31 May 2020

- Piling 46%

30 June 2020(2%)
FYNN Asoke - Construction progress as of 30 June 2020
- Piling 85%
31 July 2020(5%)
- Mobilization   100 %
- Site clearing  100 %
- Piling             100 %
-Overall progress  5%

 

18%

OF OVERALL PROGRESS

As of 31 October 2020