2020

Project Started

30 June 2022
Overall Progress: 83%
- Structural Work: 100%
- Architectural Work: 70%
- MEP Work: 71%
 
31 May 2022
Overall Progress: 78%
- Structural Work: 100%
- Architectural Work: 59%
- MEP Work: 62%
 
30 April 2022
Overall Progress: 72%
- Structural Work: 99%
- Architectural Work: 47%
- MEP Work: 51%
 
31 March 2022
Overall Progress: 68%
- Structural Work: 99%
- Architectural Work: 40%
- MEP Work: 45%
 
31 January 2022
Overall Progress: 58%
- Structural Work: 99%
- Architectural Work: 17%
- MEP Work: 33%
 
31 Dec 2021
Overall Progress: 55%
- Structural Work: 96%
- Architectural Work: 13%
- MEP Work: 27%
31 Nov 2021
Overall Progress: 49%
- Structural Work: 89%
- Architectural Work: 10%
- MEP Work: 23%
31 Oct 2021
Overall Progress: 44%
- Structural Work: 85%
- Architectural Work: 7%
- MEP Work: 10%
30 September 2021
Overall Progress: 41%
- Structural Work: 79%
- Architectural Work: 3%
- MEP Work: 8%
30 May 2021
Overall Progress: 38%
- Structural Work: 45 %
- Architectural Work: 0%
- MEP Work: 1 %
30 April 2021

- Soil Protection: 100%

- Structure: 39%

31 Mar 2021
FYNN Asoke
Construction progress as of 31st March 2021
Overall Progress: 33%
- Soil Protection: 100%
- Structure: 30%
28 Feb 2021
FYNN Asoke Construction progress as of 28th February 2021
Overall Progress: 30%
- Soil Protection: 100%
- Structure: 19%
30 Jan 2021
FYNN Asoke Construction progress as of 30th January 2021
- Overall Progress : 27.7%
- Soil Protection : 100%
- Structure : 15%
30 Dec 2020
FYNN Asoke
Construction progress is 26.9% as of 30th December 2020
 
- Soil Protection: 100%
- Pile Cutting: 55.8%
- Footing: 24.7%
30 Nov 2020


Construction progress is 22.8% as of 30th November 2020

- Cap Beam Work: 100%
- Soil Protection: 71%
- Excavation Layer B3: 17%

31 Oct 2020

- Pile wall: 100%
- Cap Beam Work: 98%
- Soil Protection: 23%

Overall progress: 18%

30 Sep 2020
- Piling  100 %
- Cap Beam Work 60%
- Overall progress  12 %
31 Aug 2020
- Mobilization  100%
- Site clearing   100%
- Piling  100 %
-Overall progress  8 %
31 May 2020(1.3%)

FYNN Asoke - Construction progress as of 31 May 2020

- Piling 46%

30 June 2020(2%)
FYNN Asoke - Construction progress as of 30 June 2020
- Piling 85%
31 July 2020(5%)
- Mobilization   100 %
- Site clearing  100 %
- Piling             100 %
-Overall progress  5%

 

100%

OF OVERALL PROGRESS

As of 31 December 2022