2016

Project Started

Feb 2, 2016 (0%)

 

  • Construction Permit Granted
  • Site Clearing Completed
Mar 17, 2016 (2%)

 

  • Piling Started
Apr 17, 2016 (4%)

 

  • Piling Test Completed
May 30, 2016 (8%)

 

  • Piling Test Completed
  • Civil Works Started
June 30, 2016 (12%)

 

  • Retaining wall completed
  • Civil works proceeded 76.7%
  • 1st Floor’s structure proceeded 57.2%
July 31, 2016 (16%)

 

  • civil works completed
  • 1st and 2nd floors' struture proceeded 65%
Aug 31, 2016 (31%)

 

  • Water treatment plant completed
  • 1st and 3th floors' structure completed
  • 4th and 6th floors' structure proceeded 70%
Sep 30 , 2016 (34%)

 

  • 1st - 7th floors' structure completed
  • 8th floor's structure proceeded 75%
  • Decorative wall proceeded 23%
Oct 31, 2016 (46%)

 

  • 1st -8th floors' structure completed
  • Rooftop's structure proceeded 90%
  • Decorative wall proceeded 56%
Nov 30 , 2016 (61%)

 

  • Decorative wall proceeded 82%
  • M&E system proceeded 77%
  • Air-conditioning proceeded 55%
Dec 31 , 2016 (72%)

 

  • Rooftop's structure completed
  • Decorative wall proceeded 91%
  • Air-conditioning proceeded 80%
Jan 31, 2017 (82%)

 

  • Decorative wall proceeded 96%
  • Decorative ceiling proceeded 82%
  • Door and window proceed 80%
Feb 28, 2017 (91%)

 

  • Decorative floor proceeded 86%
  • Air-conditioning proceeded 98%
  • Lift proceeded 65%
Mar 31 , 2017 (97%)

 

  • Decorative wall and floor completed
  • Interior (public area) proceeded 95%
  • Lift proceeded 74%
May 31, 2017 (99%)

 

  • Decorative wall, floor & ceiling completed
  • Public area's interior proceeded 99%
  • Lift proceeded 90%
100%

OF OVERALL PROGRESS

As of June 30, 2017